I (David) have learned many things since coming to South Sudan. One lesson I've learned is this – water-proofing and bug-proofing a house is a
very big task! Over the past 7 months we have built
2 new prefab houses and 1 new concrete house. Unfortunately still today none of these
houses are “perfect”. What else have I learned?
#1 Prefabs are not "weather proof" structures (even though the manufacturers website claims they are).
You can read more about my previous recommended best practices in building a prefab linked here. I can now confidently say that you can try very hard and spend a lot of time/money on silicone caulking, waterproofing bituminous tar, but the prefab will still not be perfectly watertight during the rainy season. This lead my teammates and I to decide we would build a secondary roof over the each of the prefabs.
| Front view (before) |
I knew this in Canada and its common sense. Neighbouring NGOs had hired a man named George to work for them and then prior to my arrival my teammates had hired him to weld some windows and doors on campus. With those recommendations we obtained a price from George for the work to complete the roofs. He was the only “bidder” (which isn’t ideal) but I was able to bargain with him to get a reduced price. His first price was 18,000 South Sudanese Pounds (around $4,000). But when we figured out that the work should take 25 days and when I said I thought the cost should be around 7,000 SSP, we finally agreed on a final price of 9,000 SSP (around $2,000). So we signed the contract (linked here) on Saturday July 13 and he showed up on Monday July 15 with his work crew. The contract is nothing like the 45 page legal CCDC contracts I'm used to seeing in Canada (which also have 100s of pages of specifications and drawings attached). Here it was a simple 2 pages that said "construct according to the drawings provided that may change from time to time" :)
#3 Buying materials is expensive and getting them to your construction site is not easy!
It is not uncommon in South Sudan to sign a labour-only contract (which is what we did in the case of the roofs). As a result, it was my responsibility to find cement, gravel, sand, zinc roofing sheets, roofing fasteners, welding rods, and steel support members. Fortunately we had sand, some steel and roofing sheets already on campus. I was able to buy welding rods in the local Melut market, but getting cement, gravel and roofing fasteners was a different story. For cement I had to travel by boat up the Nile River 30 minutes to a nearby town of Kaka. There I paid 250 SSP ($60) per bag of cement – way too expensive!! The non-rainy season price should be around 150 or 180 SSP per bag.
It also worked out that I was already planning a boat trip
(linked here) to the state capital of Malakal. While I was there I loaded up a
horse cart with more roofing sheets, more steel, some PVC piping for rain
gutters and 2000 roofing fasteners. My job of finding materials was complete.
| A box of 250-2" self drilling screws. This box cost me 400 SSP (about $0.50 per screw). |
#4 Good contractors can stay on schedule (and even finish
ahead of schedule)
As I said we had agreed on a 25 day schedule and George and his men started on Monday July 15 and worked 6 days a week (Mon-Sat). Yesterday (August 3) after only 18 days of work they were finished all of the work. Not bad eh?
#5 Good contractors still need to be reminded of “best practices”
There were a few times that I would check in on the guys working and one of the times I had to remind them to secure the roofing fasteners in the “top grooves” of the zinc sheets (not in the valleys). It’s obviously easier to screw into the valleys but the valleys are where all of the water drains. So after I explained that the roof would be less susceptible to water penetration if the fasteners were not in the valleys the guys agreed.
| 5 of the 6 fasteners in the bottom row are in the valleys (the wrong spot). After I told them why they should not be in the valleys they got much better! |
Here are a few photos of the progress. Enjoy!
| Steel frame completed at the Cross' prefab. At both prefabs the support posts are spaced at a maximum of 3.5m. |
This comment has been removed by a blog administrator.
ReplyDeleteI read your post its very interesting and helpful thanks for sharing such a nice information.
ReplyDeleteWhew! It looked like a lot of work, David! Thank you for sharing such in-depth opinions about how construction should be, like with roofs, which serve as the main shield to protect you from harmful weather. The ones that you did look sturdy. Good luck in future endeavors!
ReplyDeleteJoann Winton @ AJC Roofing
Nice post about Roofing Sheets thanks for sharing nice information. We are Roofing Sheets Manufacturers and Suppliers in India
ReplyDeletehey that was an interesting blog about the Roofing Sheets and you have put up some good points which will be very helpful for the General public. good job keep it up
ReplyDeleteThanks for every other informative web site. The place else may I get that kind of info written in such a perfect approach? I’ve a mission that I’m simply now working on, and I have been at the glance out for such info. Finally I read a very effective material, thank you from my heart .
ReplyDeleteאיטום גגות
Thank you for the good writeup. It in fact was a amusement account it.
ReplyDeleteLook advanced to more added agreeable from you! By the
way, how can we communicate?
Here is my web page ... beats by dre solo
Hi, yup this paragraph is truly nice and I have learned lot of things from it regarding blogging.
ReplyDeletethanks.
Here is my web site - need a job; ,
Wеll, if for example you have a weight lifting regimen that includes 12 exercises,
ReplyDeletegroup the movements in sets of 3. I'll first touch
a bit on nutritіοn and dieting since I
feel it's the most important aspect to fat loѕs.
The new trend we are seeing today is a combination between weight training and cardio is a more effective way
for burning fat.
my blog post; turbulence Training pdf